Home / Projects / Hydrotechnical construction / Water-supplies and sewerage systems / Supplying water pipeline in the town of Sungurlare, the villages of Chernitsa, Slavyantsi, Chubra, Mokren,Padarevo and Novo selo

Supplying water pipeline in the town of Sungurlare, the villages of Chernitsa, Slavyantsi, Chubra, Mokren,Padarevo and Novo selo

Contract No. RD-02-29-358 / 17.12.2012
Contractor: STANILOV – EAD Consortium
Consortium members: STANILOV LTD., EAD – Veolia

2012 - 2013

The project objective was the construction of a water pipeline of Kamchiya derivation at the  Sungurlare Inspection Pit near the field drill-range in the village of Novo Selo, which ensured the normal water supply of six settlements in the territory of the town of Sungurlare Municipality and the town of Kotel Municipality, as well as the water supply of the village of Novo Selo field drill-range. In this way, the undertaken commitments on the part of Republic of Bulgaria under the signed international agreement were fulfilled. The site construction was divided into five stages, depending on the routes of the existing and the newly designed water pipeline.
STANILOV LTD. realized the following activities:
1. Stage II: a water supply pipeline from km 19+213 to km 24+168 by laying cast-iron pipes DN300 – 2355 m of length;
2. Stage III: a water supply pipeline from km 13+239 to km 19+213 by laying of cast-iron pipes DN300 – 5974 m of length; construction of a branch to Slavyantsi Village (491 m), made of HDPE pipes – RC 100PN16, 125;
3. Stage IV: a water supply pipeline from km 6+611 to km 13+239 by laying of cast-iron pipes DN300 – 3107 m, and DN400 – 3521 m; construction of a branch to the town of Sungurlare (565 m), made of HDPE pipes – RC 100PN16, 200;
4. Stage V: a water supply pipeline from the Sungurlare Inspection Pit to km 6+611 by laying of cast-iron pipes DN400 – 6611 m and construction of a branch to the village of Chernitsa  (380 m), made of HDPE pipes – RC 100PN16, 90.